- Unpack the equipment
- Check items integrity
Determine the FTP cable length that is used to connect IDU and ODU. The total cable length between LAN (behind IDU) and ODU should not be longer than 100 meters
Figure - Connection scheme- Install (solder) connector for ODU on the FTP cable and isolate it
- Lay the FTP cable “from top to bottom” – from ODU to IDU
- After the FTP cable has been laid, use distribution box to switch from FTP cable to UTP cable with RJ-45 connectors. Service cable connecting IDU and ODU should be FTP Cat 5E cable.
- Install ODU on the mounting bracket according to the direction required for the link. Do not tight it too hard unless the antenna alignment is not complete. Install ODU connectors down.
- Connect the ODU-IDU cable to the ODU
- Isolate the ODU connector joint place
Once the ODU and antenna pole are installed they must be grounded via lightning protection grounding contour. ODU position must be lower than the highest antenna pole point at least by 2 ODU heights
Figure - Installation scheme- Connect the UTP cable to IDU
- Provide grounding for IDU
- Connect Ethernet cable to IDU
- Provide power supply for IDU
- Connect to the Device using Telnet protocol
CAUTION
It is extremely important to install ODU connectors down!